GEORGIA RAIL
PASSENGER PROGRAM |
|
|
PROGRAM MANAGEMENT
TEAM MEETING - November |
|
|
Held at the offices of the Georgia Regional
Transportation Authority |
|
|
November 7, 2002 - 1:30 p.m. |
|
| AGENDA |
|
|
|
| Chair calls meeting to order:
MINUTES
APPROVAL OF BOARD AGENDA FOR NOVEMBER 7, 2002
NEW BUSINESS AND BOARD COMMENTS
ADJOURNMENT |
|
| _________________________________________________________________________________________________________________ |
| MEETING MINUTES |
| - Notice having been duly
given, the regular meeting of the Georgia Rail Passenger Program (GRPP),
Program Management Team was held. |
|
|
|
| COMMITTEE MEMBERS PRESENT: |
|
|
| Steven Bruning |
|
|
|
| Brad Hubbert |
|
|
|
| Jimmy Lester |
|
|
|
| Carl Rhodenizer |
|
|
|
| Mather Stapleton |
|
|
|
|
|
|
|
| COMMITTEE MEMBERS ABSENT: |
|
|
| Sharon Gay, Chairman |
|
|
|
|
|
|
|
| * A quorum was present |
|
|
|
|
|
|
|
| CALL TO ORDER: |
|
|
|
| Mr. Rhodenizer called the meeting to order at 1:40 PM
|
|
|
|
|
|
|
| MINUTES: |
|
|
|
|
Motion was made by
Mr. Lester and seconded by Mr. Bruning to approve
the minutes of the October
3, 2002. The meeting minutes were approved unanimously. |
|
|
|
|
| AGENDA: |
|
|
|
- Motion was made by
Mr. Bruning and seconded by Mr. Stapleton to
approve the agenda of the
November
7, 2002. The meeting agenda was approved unanimously.
|
|
Recognition of
Guest:
Crew Heimer
introduced guests from the senior graduating class from Georgia Tech. Each
year Georgia
Tech assigns to an engineering company student engineering innovations.
Visiting today are students assigned to the Atlanta station
project.
|
- Multi-modal
Passenger Terminal (MMPT)
- The title review of the MMPT site is completed.
Meetings are being held to review the information with the
attorneys who compiled the report.
Meetings continue with area real estate developers to obtain
additional advice on the next steps relative to MMPT development.
|
- Rail
Corridor Implementation Work
- The kick-off meeting for the Macon Corridor Local
Advisory Committee (MACLAC) was held October 15, 2002 at the Griffin
Regional Welcome Center with over 30 local and regional officials
attending. Georgia Rail
Consultants briefly covered the Georgia Rail Passenger Program history
and Macon corridor status and next steps.
Various questions from the attendees focused on the roles of
localities and the timeline of development.
Consultants and staff begin to incorporate RPMC and state
agency comments on the draft Environmental Assessment for the
Athens–Atlanta line. Additional funding was provided by GRPA to
conduct a newly-required survey of the Georgia aster.
Completion of the EA process is now expected by Spring 2003.
Staff continues to update the GRPP revenues, costs, and
timeline for both commuter and intercity lines with completion of the
update expected by early December 2002.
|
|
Macon-Griffin-Atlanta
Grade Crossing Safety Implementation
Staff has met with the Georgia Department of Transportation Office of
Traffic Operations, Office of Utilities, and Districts 3 and 7 staff to
review the guiding principles and draft recommendations for grade crossing
safety. Staff has begun arranging
meetings for November and December with localities and the FRA to review
this material. The final
report for Grade Crossing Safety Implementation Plan is expected in early
2003.
|
|
SEHSR /Amtrak Issue
Data on the Charlotte-Atlanta corridor has been
obtained to developed typical train schedules to test for future
operations, and prepared for field inspection of the line.
Staff continues to work to define the role of Amtrak and Norfolk
Southern in the study. Coordination
and progress meetings are being held with other states and FRA.
|
|
Video of ADA access
at Commuter Rail stations
A video was presented to
the members of the committee to illustrate the ADA access at Commuter Rail
stations.
|
|
December GRPP
Meeting
Mr.
Stapleton requested that staff consider relocating the committee meeting
during the legislative session to allow for interaction and dialog with
new legislators. Mr. Mullins
indicated he would look at available options and report back to the
committee in December.
|
|
Adjournment:
There being no further
business to come before the Project Management Team, the meeting adjourned
at 2:10 pm. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|