| Macon to Atlanta Rail Corridor | ||||||||||||||||||||||
| Macon
Commuter Rail Service |
||||||||||||||||||||||
The 104-mile
Macon line is forecast to carry 8,000 commuter rides each weekday in the
year 2010, equal to 10% of the peak hour/direction traffic on parallel
highways. The commuter rail
will provide the equivalent capacity of two general-purpose highway lanes.
The Macon line also provides the spine of a first tier of intercity
rail lines to Albany, Columbus, Savannah, and Jacksonville that was
adopted by the Board of Transportation in the Intercity Rail Plan of 1995
and included in the three-agency Program Management Team’s 1999 Georgia
Rail Passenger Program (See GRPP
Fact Sheet).
Fares based
on distance are shown in the table on the right.
|
||||||||||||||||||||||
|
|
Sample Macon Corridor average fares to Atlanta one-way: |
|||||||||||||||||||||
|
|
|||||||||||||||||||||
| Capital costs are estimated at $290 million in year 2000 dollars. The major categories of this cost are shown in the table on the next page, with each category including all costs of design, construction management, and contingency attributable to each. | ||||||||||||||||||||||
| Current Activities and Implementation Schedule | ||||||||||||||||||||||
|
Major
activities underway consist of station area planning, public and
neighborhood outreach, railroad capacity improvement study, and Federal
permitting and funding. Station area planning: Specific location of stations, size and arrangement of parking facilities, provision of feeder and distribution bus service, and the development of transit-oriented land uses are being discussed with local and county planners and transportation agencies. |
||||||||||||||||||||||
| Sample Macon Corridor AM rush hour schedule: | Public
and neighborhood outreach:
Rail planners are meeting with local neighborhood homeowner
associations and local officials, publishing a newsletter and maintaining
a website, ( www.garail.com ), and
holding advertised public meetings in order to provide current project
information and identify public concerns and issues so that they can be
properly addressed. |
|||||||||||||||||||||
|
Station |
Time | |||||||||||||||||||||
|
|
|
|
|
|
|||||||||||||||||
| Railroad
capacity improvement study:
The Norfolk Southern railroad that owns the right of way and tracks
to be used for the commuter rail service has agreed to work with the state
on a capacity improvement study to determine what specific investments
will be needed to accommodate commuter rail and future freight traffic
growth. This work will update
the current estimates of how much additional track, signalling,
grade-crossing upgrades, and other improvements are needed. |
||||||||||||||||||||||
| Federal
permitting and funding:
Work is progressing on the environmental assessments needed in
order to use the Federal funds programmed for the Macon commuter service
in the Atlanta region’s Transportation Improvement Plan.
The Federal Transit Administration will administer the Federal
capital funds that must be matched by State and local funds. |
||||||||||||||||||||||
|
Also
being defined are the specifications and numbers of locomotives and train
cars needed, and operations financing options.
Federal
environmental clearance is anticipated for Spring 2002, at which point
funds can be committed to the longer lead time items of train equipment
and facilities design. Service
is anticipated to begin in late 2003 from Griffin, and from Macon in 2004,
provided state funding is provided as requested. |
|||||||||||||||||||||
| FY
2002 Funding Requests |
||||||||||||||||||||||
|
||||||||||||||||||||||
|
Preliminary Engineering Total cost for FY 2002 is $6 million ($1.2 million in state general funds) for preliminary engineering of improvements described in the Trackwork / Signals/ Construction section below for FY 2002, and a portion of Trackwork / Signals / Construction work to be funded in FY 2003 and FY 2004. Right of Way Total cost for FY 2002 is $10 million ($2 million in state general funds) for acquisition of additional right of way in the Mountain View to Hapeville section to accommodate a second main track and to begin the acquisition of property at stations required to accommodate parking, and layover facilities in Griffin and Macon. Rolling Stock Total cost for FY 2002 is $30 million ($6 million in state general funds) which is for the procurement, inspection, and acceptance testing of a first order of passenger train equipment consisting of 4 diesel-electric passenger locomotives at an estimated $2.9 million each, four double-deck coaches with driver’s cab to allow full speed reverse direction operation at $2.3 million each, and six regular double-deck coaches at $1.7 million each.
|
||||||||||||||||||||||